NV C-5 Concrete Practice Questions - Nevada C-5 Concrete Contractor Examination Exam

Access More Questions
Engineered fill under a C-5 building slab is specified at 95 percent of ASTM D1557 in 8-inch maximum loose lifts. After three lifts, a loaded water truck leaves 2-inch ruts and pumping. What should the contractor do?
Correct Answer:
Stop, rework or replace the failing lift until a proof-roll shows a firm, non-yielding surface, then continue in specified lifts