SC Bridges Practice Questions - South Carolina Bridges Contractor Examination Exam

Access More Questions
During final placing of solid-web structural members, OSHA 1926.756 requires the load to remain on the hoisting line until the member is secured with at least how many bolts per connection?
Correct Answer:
Two bolts per connection, drawn up wrench-tight unless a competent person requires more

Access more questions from this quiz

Continue to SC Bridges Practice Questions - South Carolina Bridges Contractor Examination Exam for more practice questions and the full quiz experience.

Access More Questions