During a pre-construction meeting, which of the following is NOT typically a primary responsibility of the architect?
Correct Answer:
Verifying the contractor's means and methods
Explanation:
The architect is responsible for design intent, while the contractor is exclusively responsible for construction means, methods, techniques, and safety.