Direct labor is $40,000, materials are $65,000, subcontractors are $55,000, and direct equipment cost is $10,000. What is total direct job cost?
Correct Answer:
$170,000
Explanation:
$40,000 + $65,000 + $55,000 + $10,000 = $170,000.