Before concreting, workers should check the elevation of the subbase by:
Correct Answer:
measuring down from a straightedge spanning between the side forms
Explanation:
Setting the subbase elevation relative to the formwork is essential to ensure the finished slab thickness matches the design. Using a straightedge that spans between the side forms provides a fixed reference plane that represents the intended top surface of the slab. By measuring from that straightedge down to the subbase at several points, you verify whether the subbase sits at the correct height. If the measured distance isn’t within tolerance, you adjust the subbase and recheck before pouring. This method is practical on site because it gives a direct, repeatable measurement tied to the actual finished surface. A string line helps with alignment but doesn’t give a reliable elevation check. A laser level can work, but requires setup and calibration. Measuring from the top of the forms is less reliable since form heights can vary.

Access more questions from this quiz

Continue to Concrete Flatwork Technician and Flatwork Finisher Practice Test for more practice questions and the full quiz experience.

Access More Questions