Before breaking ground for a private water or sewer trench in West Virginia, an excavator must notify the statewide one-call system (WV 811 / 811) at least how far in advance?
Correct Answer:
Not less than 48 business hours, exclusive of Saturdays, Sundays, and legal holidays