At a tank wall pipe penetration the bar cage is so congested that a 1-1/2-inch vibrator cannot enter and rock pockets are likely. What should the contractor do?
Correct Answer:
Stop and resolve congestion with the engineer (spacing, bundling, or a placement opening) before placing concrete