ANSI/AWWA C600 hydrostatic testing of a new ductile-iron water main requires the test pressure to be held at least 2 hours and to be not less than:
Correct Answer:
1.25 times the working pressure at the highest point of the test section and 1.5 times the working pressure at the lowest point of testing