An IT governance board in a Hong Kong financial institution is evaluating two software development projects. Project A has an initial investment of HK$2,000,000 and a Net Present Value (NPV) of HK$450,000. Project B has an initial investment of HK$3,500,000 and an NPV of HK$600,000. Based strictly on the Net Present Value rule, which project should the board select?
Correct Answer:
Project B, because it has a higher Net Present Value, which maximizes wealth creation.