NM CID MM-2 Practice Questions - New Mexico CID MM-2 Natural Gas Fitting Examination Exam

Access More Questions
An existing low-pressure house main was sized for 90 CFH. The owner adds a 50,000 Btu/h (50 CFH) decorative appliance. What must you do before connecting it?
Correct Answer:
Recheck the existing piping capacity for the new total load using the same longest-length table row, and enlarge any undersized section

Access more questions from this quiz

Continue to NM CID MM-2 Practice Questions - New Mexico CID MM-2 Natural Gas Fitting Examination Exam for more practice questions and the full quiz experience.

Access More Questions