An excavation contractor needs to haul 2,000 bank cubic yards (BCY) of silt loam (swell factor 15%) from a residential subdivision. If each dump truck has a legal payload capacity of 14 loose cubic yards (LCY), how many total truck trips are required?
Correct Answer:
165 trips