An earthwork contractor needs to fill a structural pad with 2,700 compacted cubic yards (CCY) of soil. If the soil material has a shrinkage factor of 10%, how many bank cubic yards (BCY) of excavation are required?
Correct Answer:
3,000 bank cubic yards