According to the ACPA Concrete Pipe & Box Culvert Installation manual, where should placement of a gravity concrete-pipe line start, and which way should the bells face?
Correct Answer:
Start at the outlet end, with the bell pointing upstream and the spigot or tongue pointing downstream