According to NR-10 item 10.5.1, what is the mandatory chronological sequence of procedures required to formally consider an electrical installation de-energized before maintenance?
Correct Answer:
1) Disconnection; 2) Lockout and tagout; 3) Verification of voltage absence; 4) Installation of temporary grounding; 5) Protection of adjacent live elements; 6) Signage and signaling.