Categories
All Categories
DMV
ServSafe
OSHA
NCLEX
HESI
TEAS
ATI Nursing
CNA & Nurse Aide
NREMT & EMS
ACLS
BLS
CPR
Quizzes
Study Guides
Flashcards
Packages
0
Log In
Register
Categories
All Categories
DMV
ServSafe
OSHA
NCLEX
HESI
TEAS
Quizzes
Study Guides
Flashcards
Packages
Contact
Cart
0
Log In
Register
MASS Test
Access More Questions
Report question problem
×
I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
According to Massachusetts Dig Safe law (M.G.L. c. 82, § 40A), what is the minimum required notice an excavator must provide to the Dig Safe system before starting a non-emergency excavation?
48 hours, including weekends and holidays
At least 24 hours, but not more than 30 days
72 hours, excluding Saturdays, Sundays, and legal holidays
One full business week (5 business days)
Reveal Answer
Correct Answer:
72 hours, excluding Saturdays, Sundays, and legal holidays
Access more questions from this quiz