A wall-form drawing limits the rate of rise to 5 feet per hour. The crew has a 10-foot wall and wants to finish in one hour. What should the C-5 contractor do?
Correct Answer:
Hold the pour to 5 feet per hour, or obtain a revised form design that is good for the faster rate, because pressure rises with R