A UUC contractor has placed empty Schedule 40 PVC sleeves under a new parking lot. The owner then asks the same crew to pull 480-volt feeder conductors through those sleeves and terminate them on an energized switchboard. What is the correct scope decision?
Correct Answer:
The empty sleeves were inside UUC, but installing conductor wiring and connecting to an energized electrical system is outside UUC