A team has a development column with WIP limit 3. A developer finishes a task in 'In Progress' and wants to pull a new item from the backlog, but 'Code Review' is already at its WIP limit. What is the correct Kanban behavior?
Correct Answer:
Do not pull new work; instead, help unblock 'Code Review' so work can flow downstream