A project team is applying optimism bias to a capital cost estimate in an Outline Business Case for a new road project. The HM Treasury Green Book supplementary guidance gives an upper bound of 44% for standard civil engineering works. The base estimate before risk is £20 million. What is the optimism-bias-adjusted cost?
Correct Answer:
£28.8 million