A project specification and a coating manufacturer's current product data sheet appear to conflict on the allowable recoat interval. What should the inspector do?
Correct Answer:
Document the conflict and request clarification through the established chain of communication before accepting the work
Explanation:
The inspector should identify and document conflicts among governing documents and obtain an authorized clarification. The inspector should not independently rewrite project requirements.