A stakeholder repeatedly requests changes to the project scope, causing delays and budget overruns. The project manager has documented these requests and their impacts, but the stakeholder continues to make additional requests. What should the project manager do next?
Correct Answer:
Implement a formal change control process and communicate it to all stakeholders