A project has an Earned Value (EV) of 250,000 QAR, an Actual Cost (AC) of 280,000 QAR, and a Planned Value (PV) of 260,000 QAR. What is the Cost Variance (CV) for this project?
Correct Answer:
-30,000 QAR