Categories
All Categories
DMV
ServSafe
OSHA
NCLEX
HESI
TEAS
ATI Nursing
CNA & Nurse Aide
NREMT & EMS
ACLS
BLS
CPR
Quizzes
Study Guides
Flashcards
Packages
0
Log In
Register
Categories
All Categories
DMV
ServSafe
OSHA
NCLEX
HESI
TEAS
Quizzes
Study Guides
Flashcards
Packages
Contact
Cart
0
Log In
Register
PgMP Practice Questions - Program Management Professional Exam
Helpsheet
×
Helpsheet
×
Report question problem
×
I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
Question Number 5
A program manager discovers that the organization's strategic priorities have shifted significantly. What should the program manager do FIRST?
Continue executing the program as planned since it was already approved
Assess the impact of the strategic shift on the program's alignment and benefits
Escalate to the project managers to adjust their individual project plans
Close the program immediately to avoid wasting resources
✔ Correct Answer:
Assess the impact of the strategic shift on the program's alignment and benefits