A planning manager is overseeing a complex project to update the city's zoning ordinance. The project involves numerous sequential tasks with clear dependencies. To effectively schedule the project, identify the longest sequence of dependent tasks, and determine the minimum time to completion, which project management tool would be most appropriate?
Correct Answer:
PERT Chart