A piping isometric bill of materials lists: 2 – NPS 4 LR 90, 1 – NPS 4 tee, 12 ft of NPS 4 Sch 40, and 2 – NPS 4 Class 150 WN RF flanges. What is the first takeoff check a fitter should make?
Correct Answer:
Verify that the counted fittings, flanges, and cut lengths match the drawn geometry after elbow and flange takeoffs are subtracted