A new South Carolina water-and-sewer project will take more than 90 days and includes more than 1 mile of utility infrastructure in an area with underground facilities. What advanced-notice duty applies?
Correct Answer:
Notify the notification center at least 30 days before starting and set a planning meeting within 15 days of that notice