Access More Questions
A local authority is short-listing options for a leisure centre redevelopment. After applying Critical Success Factors, four options remain on the short list. The NPVs at 3.5% Green Book discount rate are as follows: Option A −£4.2 m, Option B −£3.8 m, Option C −£5.1 m, Option D −£3.8 m. Based solely on the monetary appraisal, which option or options should be identified as the preferred option?
Correct Answer:
Option B or Option D, because they share the lowest net present cost