A homeowner contracts with a builder to construct a custom home for $300,000. After substantial performance, the builder uses the wrong brand of pipe (functionally identical) and the homeowner refuses to pay. Under common-law contract principles tested on the MBE, what is the homeowner most likely required to do?
Correct Answer:
Pay the contract price minus the diminution in value caused by the immaterial breach