A GF-5 contractor is the only licensee on a park project whose largest dollar share is a new restroom building with full plumbing and electrical. What does NMAC 14.6.6.8 require?
Correct Answer:
The GF-5 contractor may bid as prime only if the major portion by dollar amount is GF-5 work, and must subcontract plumbing and electrical to validly licensed contractors