A general engineering contractor is preparing a bid for a site excavation job requiring the movement of 45,000 bank cubic yards (BCY) of earth. Soil swelling factor is 20%. If hauling trucks carry 15 loose cubic yards (LCY) per trip, how many total truck trips are needed?
Correct Answer:
3,600 trips