ICDL Practice Test & Exam Prep | Ireland
Helpsheet
×
Helpsheet
×
Report question problem
×
I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
Question Number 5
Task 'Install signage' in a Waterford retail rollout shows 4 days of total float. What does that mean for the project finish date?
The task may slip up to 4 working days without pushing out the project end
The task must finish within 4 days of starting or it becomes critical
The assigned painter is overallocated by 4 hours per day
The software will extend the task duration by 4 days automatically
✔ Correct Answer:
The task may slip up to 4 working days without pushing out the project end
Count Down:
Related questions :