SC Wood Frame Structures Practice Questions - South Carolina Wood Frame Structures Contractor Examination Exam

Access More Questions
A crew is ready to pour continuous wall footings. The trench bottom is frozen and contains pockets of topsoil. What is the correct action before placing concrete?
Correct Answer:
Remove frozen soil and organic/topsoil and bear the footing on firm, undisturbed mineral soil or engineered fill, then place concrete