A cooling-coil drain pan is installed above a finished ceiling. If overflow from a clogged primary drain could damage the building, IMC 307 requires which of the following?
Correct Answer:
An auxiliary drain pan with a separate drain, a secondary drain from the pan, or a listed water-level detection device that shuts off the equipment