ND General Contractor Practice Questions - North Dakota General Contractor Exam

Access More Questions
A contractor's project has $350,000 direct costs and $50,000 overhead. With 10% profit, what is the total bid?
Correct Answer:
$$440,000

Access more questions from this quiz