A contractor must place 2,500 compacted cubic yards (CCY) of structural embankment fill for a residential access road. The borrow pit soil has a shrinkage factor of 15% relative to bank measure and a swell factor of 20% from bank to loose measure. How many loose cubic yards (LCY) of borrow soil must be hauled to the site?
Correct Answer:
3,529 LCY