A contractor agrees to build a custom machine for a buyer for $100,000. After the contractor has spent $40,000 and substantially begun work, the buyer repudiates without cause. Which measure of damages best compensates the contractor's expectation interest?
Correct Answer:
The contract price less the cost the contractor saved by not completing performance