A contract manager for a Texas state agency discovers that a major deliverable from a contractor is three weeks behind schedule, which could jeopardize the project's overall timeline. According to sound contract administration principles, what is the contract manager's most appropriate initial action?
Correct Answer:
Document the delay and communicate with the contractor to understand the cause and discuss corrective actions.