NV B General Building Practice Questions - Nevada B General Building Contractor Examination Exam

Access More Questions
A continuous wall footing is 100 feet long, 24 inches wide, and 12 inches thick. How many cubic yards of concrete are required (no waste)?
Correct Answer:
7.4 CY

Access more questions from this quiz

Continue to NV B General Building Practice Questions - Nevada B General Building Contractor Examination Exam for more practice questions and the full quiz experience.