AZ ROC C-9 Concrete Practice Questions - Arizona ROC C-9 CR-9 R-9 Concrete Examination Exam

Access More Questions
A continuous perimeter footing has a total centerline length of 200 linear feet, a width of 24 inches, and a depth of 12 inches. If a 5% waste factor is included in the material takeoff, what is the total volume of concrete required?
Correct Answer:
15.6 cu yd

Access more questions from this quiz

Continue to AZ ROC C-9 Concrete Practice Questions - Arizona ROC C-9 CR-9 R-9 Concrete Examination Exam for more practice questions and the full quiz experience.