A construction project requires excavating 5,000 cubic yards of soil in its bank (in-place) state. The soil has a swell factor of 1.4 (1 bank cy expands to 1.4 loose cy when excavated). How many cubic yards of loose soil must be hauled away?
Correct Answer:
7,000 cy