PE Civil Practice Questions - PE Civil Engineering Exam

Access More Questions
A concrete mix design requires 350 lbs of cement per cubic yard. For a 100 cubic yard pour with 8% waste factor, how many 94-lb sacks of cement are required?
Correct Answer:
403 sacks

Access more questions from this quiz

Continue to PE Civil Practice Questions - PE Civil Engineering Exam for more practice questions and the full quiz experience.

Access More Questions