A concrete contractor is estimating the concrete volume required for a building slab measuring 40 feet wide by 60 feet long with a specified thickness of 6 inches. Allowing a 10% waste factor for subgrade irregularities and spillage, how many cubic yards of concrete should be ordered?
Correct Answer:
48.9 cu yd