A CMRS is estimating a remediation job that requires removing mold-contaminated drywall from 400 sq ft of wall area and replacing it with new drywall. Which cost component is MOST OFTEN underestimated by new supervisors?
Correct Answer:
Hours required to build, maintain, and tear down critical barriers (containment)