A canal project’s earthwork estimate shows 40,000 bank cubic yards of cut and 42,000 compacted cubic yards of embankment needed. If the soil shrinks 10 percent from bank to compacted fill, about how much borrow is required?
Correct Answer:
About 6,000 compacted cubic yards of borrow