A bent has 8 prestressed concrete piles. Plan tip-to-cutoff length is 52 ft each. The contractor must furnish 3.0 ft of driving/cutoff allowance per pile. Piles cost USD 48 per furnished foot. What is the pile material cost?
Correct Answer:
USD 21,120