A Beaufort contractor will jet and drive piles near a marked subaqueous utility under a tidal creek. Under S.C. Code § 58-36-60, notice to SC811 must be made within which window, not counting the day notice is given?
Correct Answer:
Ten to twenty full working days before commencement

Access more questions from this quiz