A backhoe nicks a marked gas service while a water main is being laid. Besides protecting people and calling 911 if there is a release, what must the excavator do under the SC811 Excavator Manual?
Correct Answer:
Notify SC811 and the facility operator immediately, submit a damage report, and do not backfill the damaged facility until the operator authorizes it