A homeowner contracts with a builder to construct a house, but the builder substantially completes the work with a minor, non-willful deviation (using a different but equivalent brand of pipe). The homeowner refuses to pay anything. Under the doctrine of substantial performance, what is the builder entitled to?
Correct Answer:
The contract price minus damages for the minor deviation