A 3/4-inch base plate will sit on a 1-inch grout pad. The nut-and-washer stack is 1-1/2 inches, and 1/2 inch of thread must extend beyond the nut. What minimum anchor-rod projection above the concrete is required?
Correct Answer:
3-3/4 inches