City of Lancaster specifications that adopt SCDOT Section 501 restrict placement when the base or air in the shade is 40°F and falling, or when air in the shade is 95°F and rising or concrete temperature exceeds 95°F. What is the contractor's correct response at 96°F rising air with a 97°F mix?
Correct Answer:
Do not place; use hot-weather controls, night paving, or mix adjustments and wait until temperatures comply